Project Overview:
Balaji Ginning and Pressing Industry, located in Nandura, Maharashtra, is a key player in the ginning and pressing sector. In a bid to reduce energy costs and promote sustainability, the company decided to invest in solar energy. Chirayu Power Pvt. Ltd. was selected to install a 440 kW solar system at their facility, which includes a 150 kW single-axis tracker system — the first of its kind in the Vidarbha region.
The single-axis tracker system ensures that the solar panels track the sun’s movement, generating 25% more electricity compared to traditional fixed systems. This system helped Balaji Ginning and Pressing reduce electricity costs while improving energy efficiency and contributing to a greener future.
Total Installed Capacity: 440 kW
1. Panels:
- Waaree Energy 335 Wp Polycrystalline (for 150 kW system)
- Waaree Energy 450 Wp Half-Cut Panels (for 290 kW system)
2. Inverters:
- SolarEdge Optimization Inverters (for 150 kW system)
- Havells Inverter 100 kVA x 3 Nos. (for 290 kW system)
3. Power Optimizer: P730 Optimizer (2/1)
4. Completion: 2018 & 2022
Project Summary:
In 2018, Chirayu Power Pvt. Ltd. installed a 150 kW solar system with the first single-axis tracker system in the Vidarbha region for Balaji Ginning and Pressing Industry. This SolarEdge optimization inverter system with Waaree Energy 335 Wp panels tracked the movement of the sun throughout the day, generating up to 25% more energy.
After 2.5 years of successful operation, Balaji Ginning and Pressing returned to Chirayu Power for an additional 290 kW of solar capacity. The 290 kW system was equipped with Waaree Energy 450 Wp half-cut panels and Growatt string inverters to further enhance their energy generation.
We are extremely grateful to Balaji Ginning and Pressing for their trust in Chirayu Power and their commitment to adopting sustainable practices. Their positive experience with our friendly approach and technical expertise led them to award us even larger and smaller projects.
Key Features of the Solar Solution
1. Single-Axis Tracker:
First solar tracker system in Vidarbha, allowing the panels to follow the sun’s movement, generating 25% more energy than traditional systems.
2. Ground-Mounted Structure:
Super galvanized structure used for the 150 kW ground-mounted system, providing durability and strength to withstand weather conditions and ensure optimal performance.
3. Rooftop Structure:
Aluminum short rail structure used for the 290 kW rooftop system, ensuring lightweight support with a flush-mounting design for optimal energy generation.
4. Walkway:
- FRP walkways used for easy and safe maintenance access.
5. Railing Protection:
- MS-coated railings for worker safety during rooftop maintenance.
6. Earthing Kit:
- Pipe-in-pipe chemical earthing system with discom-approved earthing powder and copper plates.
7. Lightning Protection:
- ESE Lightning Arrestor with a 107m protection radius and copper arrestors for added protection.
8. Cabling:
- TUV-certified cables for AC and DC connections, ensuring high performance and safety.
9. Monitoring System:
- Module-level monitoring using SolarEdge optimizers and Havells inverters, enabling real-time tracking and performance optimization.
Expected Generation and Benefits of the Solar Project
The 440 kW solar system offers Balaji Ginning and Pressing Industry significant benefits:
Energy Cost Savings: The system has resulted in a substantial reduction in electricity costs, saving more than ₹5 Lakh per year.
Environmental Sustainability: By adopting solar energy, the company has significantly reduced its carbon footprint, aligning with global sustainability goals.
Reliable Power Supply: The system provides continuous power generation, reducing dependency on grid electricity and improving operational efficiency.
Carbon Footprint Offset: The 440 kW solar system is equivalent to planting approximately 6,600 trees (440 kW * 15 trees per 1 kW), benefiting the environment.
Performance and Savings
Over the last 3 years, Chirayu Power Pvt. Ltd. has successfully operated the 440 kW solar system at Balaji Ginning and Pressing, generating approximately 5.7 lakh units per year.
Annual Savings: The system saves the company about ₹5 Lakh per year on electricity bills, demonstrating the system’s efficiency and cost-effectiveness.
Conclusion
The successful installation and ongoing operation of the 440 kW solar system at Balaji Ginning and Pressing Industry demonstrates the power of solar energy in reducing operational costs, improving energy efficiency, and supporting sustainability. With SolarEdge technology, high-efficiency panels, and excellent post-installation support, Chirayu Power Pvt. Ltd. delivered a solar solution that meets the client’s energy needs and enhances operational efficiency.
We sincerely appreciate the trust that Balaji Ginning and Pressing has shown in us. Their decision to invest in solar energy was not just a step towards cost savings, but also a green decision that is helping the environment. We look forward to continuing this successful partnership and helping them expand their solar energy footprint even further.
For more information or to discuss how we can help your business transition to solar energy, contact us at Chirayu Power Pvt. Ltd. today!
This project serves as a leading example of how solar energy can provide substantial cost savings while promoting sustainability in industrial operations.
Performance Recap:
The solar system at Balaji Ginning and Pressing has been generating 5.7 lakh units per year, resulting in ₹5 Lakh in annual savings and supporting their commitment to a greener, more sustainable future.